Kentucky’s plumbing code requires a secondary roof drain or scupper wherever the roof perimeter would let water pond if the primary drains plug — on its own piping, discharging where someone will actually see it.

Standing water on a flat commercial roof is usually treated as a membrane problem. Often it is a drainage-code problem wearing a membrane problem’s clothes. The rules are short, specific and already law in Kentucky, and they tell you what to look for before anybody quotes a reroof.

Does a Kentucky commercial roof need a secondary roof drain?

Yes, where the roof perimeter construction allows ponding if the primary roof drains become blocked. Secondary drains or scuppers are required in that case.

The requirement is in Section 8 of 815 KAR 20:130, the Kentucky State Plumbing Code regulation on house sewers and storm water piping, whose current version took effect June 2, 2020. The relevant subsection reads: “Secondary (emergency) roof drains or scuppers shall be provided where the roof perimeter construction allows ponding if the primary roof drains become blocked.”

That describes most parapet-walled commercial roofs in Central Kentucky. A parapet is roof perimeter construction that holds water in. If the internal drains plug with leaves or ice and nothing else moves the water, the roof becomes a tank — and a flat roof carrying several inches of water is carrying weight it was not designed to hold indefinitely.

What does the code require of the secondary system?

Separate piping, a separate point of discharge, and a discharge above grade plane in a spot occupants or maintenance staff would normally see.

Section 8 spells both halves out. “Secondary roof drain systems shall have piping and point of discharge separate from the primary system,” and “discharge shall be above grade plane in a location that would normally be observed by the building occupants or maintenance personnel.”

The second half is the design intent in one line: water coming out of an emergency drain is a visible alarm. If the overflow is tied into the same leader as the primary drain, or it dumps somewhere nobody walks, the building loses the only free warning it had that the primary drains are blocked.

An emergency drain that discharges where nobody can see it still meets the plumbing plan. It does not meet the code, and it does not warn anyone.

What does the code say about the drains and strainers themselves?

Strainers must extend at least four inches above the roof surface next to the drain, with an open area of at least one and a half times the leader they feed.

Section 8 again, on both primary and secondary drains: strainers “extending not less than four (4) inches above the surface of the roof immediately adjacent to the roof drain,” with “an available area not less than one and one-half (1 1/2) times the area of the conductor or leader to which the drain is connected.” Decks that are normally serviced and maintained — sun decks, parking decks and similar areas — may instead use flat-surface strainers installed level with the deck, and those need an available inlet area of at least two times the leader area.

Two field consequences. A crushed or missing dome strainer is not cosmetic; it is the part that keeps the leader from plugging. And a flat strainer dropped into a roof that is not a serviced deck is the wrong part in the wrong place.

How big does the leader have to be?

The code sizes it by drained roof area, in a table. An inside leader serving 1,801 to 3,600 square feet of roof is four inches.

Area of roof (square feet)Leader diameter (inches)
Up to 901 1/2
91 to 2702
271 to 8103
811 to 1,8003 1/2
1,801 to 3,6004
3,601 to 5,5505
5,501 to 9,6006
Size of rain water leader, 815 KAR 20:130 Section 21, as published by the Kentucky Legislative Research Commission; current version effective June 2, 2020.

Inside conductors and roof leaders are also restricted by material. Where a conductor or leader runs within the walls of a building, or in an interior court or ventilating shaft, the regulation lists what it may be built of — cast iron, galvanized wrought iron, galvanized steel, copper, Schedule 40 ABS or PVC DWV among them. A roof repair that re-routes an interior leader is a plumbing-code decision as much as a roofing one.

Where is roof water allowed to go?

Into a storm water system, a combined sewerage system, or a surface drainage area — never into a sewer intended for sewage only.

Section 20 of the regulation sets that out directly: a roof, paved area, court or courtyard shall be drained into a storm water system, a combined sewerage system, or a surface drainage area unless the local health department or sewer district prohibits it — and “a yard, roof, paved area, court, or courtyard shall not be drained into a sewer intended for sewage only.” If a drain is connected to a combined sewerage system it has to be trapped, and a trap must be set below the frost line or inside the building.

That last clause is the one that catches older buildings here. Local sewer districts have spent years separating storm flow from sanitary flow, and a downspout or roof drain tied into a sanitary-only line is both a code violation and, increasingly, a utility enforcement matter. Verify where the water goes before the reroof, not after.

A walkable checklist for a ponding roof

  • Count the drains, then count the overflows. A parapet roof with primary drains and no scuppers or secondary drains is the condition Section 8 addresses.
  • Look at where the overflow discharges. Separate piping, above grade plane, somewhere people pass.
  • Check every strainer: present, undamaged, standing proud of the roof surface rather than flattened into it.
  • Match leader size against drained area using the table above before accepting that the roof “just drains slowly.”
  • Trace the discharge. Storm or combined is allowed; sanitary-only is not.

None of this replaces a licensed plumber’s judgment, and the plumbing code is enforced by plumbing inspectors, not by roofers. What it does is tell a building owner which questions have a written answer. The Kentucky Department of Housing, Buildings and Construction, the agency behind the state plumbing code, is where the regulation and its inspection program live.

For public buildings the money side runs on separate rails, which we walked in commercial roofing on a public building and the lien that replaces it. If what you have is an active leak rather than a drainage question, start with roof repair.

Are scuppers an acceptable substitute for a secondary drain?

815 KAR 20:130 Section 8 names both: “Secondary (emergency) roof drains or scuppers shall be provided where the roof perimeter construction allows ponding if the primary roof drains become blocked.” Which one fits a given roof is a design question for the plumbing designer and inspector.

Can the overflow drain tie into the primary downspout?

No. The regulation requires secondary roof drain systems to have piping and a point of discharge separate from the primary system, with the discharge above grade plane where occupants or maintenance personnel would normally observe it.

Can roof water drain into the sanitary sewer?

No. Section 20 of 815 KAR 20:130 states that a yard, roof, paved area, court or courtyard shall not be drained into a sewer intended for sewage only. Permitted destinations are a storm water system, a combined sewerage system, or a surface drainage area unless the local health department or sewer district prohibits it.

Last updated November 10, 2026.

By Central Roof Repair · Roof repair across Central Kentucky · Call or text (859) 310-1209.

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *